Aarhus Municipality
Cycle paths Holmevej
School Road Project. Stage 2 of establishing one-way cycle paths and new sidewalks
School Road Project. Stage 2 of the establishment of one-way cycle paths and new sidewalks on Holmevej, on the stretch between the intersection at Holmevej/Rundhøj Allé/Filippavej to Skovriddervej at Carl Nielsens Vej, as well as 2 new traffic lights at Holmevej/Rundhøj Allé/Filippavej and Holmevej/Rosenvangs Allé, as part of the school road analysis 2017.
​
The contract included the following main works and quantities:
​
-
Traffic management including signal regulations
-
Clearing and pruning of vegetation
-
Demolition and disposal of asphalt approx. 5,700 m²
-
Asphalt cutting approx. 2,700 meters
-
Stair milling approx. 1,500 meters
-
Demolition of curbs approx. 2,850 meters, of which approx. 2,200 meters will be reused
-
Demolition and disposal of concrete pavements approx. 2,600 m²
-
Breaking up paving stones approx. 250 m²
-
Excavation and disposal of surplus soil approx. 2,900 m³
-
Decommissioning of wells, for example, approximately 35 units.
-
Establishment of drainage pipe approximately 300 meters
-
Establishment of drains approximately 900 meters
-
Establishment of new drain wells, approximately 70 units.
-
Establishment of Cable Pipe approx. meters
-
Underboring approx. 24 pcs.
-
Burial/handling of supply cable approx. 600 meters
-
Establishment of cable wells approx. 14 pcs.
-
Installation of signal mast foundations approx. 15 pcs.
-
Dismantling/moving lighting masts approx. 12 pcs.
-
Delivery and installation of bottom protection approx. 1,750 m³
-
Delivery and installation of stabilized gravel approx. 8,850 m²
-
Installation of granite/concrete curbs approximately 2,800 meters
-
Laying of paving tiles/concrete paving with tactile areas approx. 2,650 m²
-
Laying of paving stones 1-2-3 rows as a table/walking path approximately 2,200 meters
-
Laying of GAB asphalt base course approx. 5,600 m²
-
Laying of ABB binder course approx. 750 m²
-
Laying of AB wearing course approx. 5,900 m²
-
Establishment of asphalt ramps approx. 1,200 m²
-
Establishment of various signs, approximately 55 pieces.
-
Establishment of Thermo plastic striping div width approx. 1,400 meters
-
Establishment of barrier surfaces etc. approx. 110 m²
-
Establishment of Thermo plastic symbols approx. 25 pcs.