Skanderborg Cooperative Housing Association

Roundabout on Virringvej

Redevelopment of the intersection between Virringvej, Sigkærgårdsvej and Tårnfalkebakken in Skanderborg into a roundabout

The project includes intersection reconstruction, rainwater management in the roundabout, and various adjustments in all four access branches, including the adjustment of the existing two-way cycle path so that it will be directed to the roundabout in the future.

​

The contract includes the following main works and quantities:

​

  • Establishment of traffic control measures

  • Clearing of existing plantings and pavements

  • Breaking up of approx. 1,100 m² of asphalt and unbound base layers

  • Removal of approximately 150 m³ of soil

  • Excavation of approximately 450 m³ of raw soil

  • Regulation and compaction of approximately 1,650 m² of roadbed

  • Adaptation of existing noise barriers and construction of new noise barriers

  • Coordination with relevant utility companies in connection with the relocation of wires and cables

  • Laying of approximately 100 lbm of rainwater pipes ø160 mm

  • Laying of approximately 225 lbm of drainage pipes in filter gravel

  • Cancellation of five road drainage wells and installation of eight new gutter wells and two new drainage wells

  • Laying of approx. 800 m³ of bottom protection and approx. 1,525 m² of SG II

  • Laying of approximately 2,900 m² of asphalt

  • Setting of approximately 75 lbm curbstone

  • Establishment of new roadway markings and restoration of road signs and three lighting masts

  • Laying out approx. 400 m² of soil on flower beds, slopes, etc. including grass seeding.

Developer

Skanderborg Cooperative Housing Association

Adviser

Engineering firm Jönsson A/S

Contract type

Main contract

Execution period

August – October 2021

Competence
bottom of page